S10-21, Step 1-3 (Riveting bellcrank and skins)

Got to do some work with the pneumatic squeezer again. It’s really not often that I get to do that, so it was a great switch from pounding with the rivet gun.

Today I set some rivets in the nutplates to the F-1037B & Bellcrank Rib Angles, and also the F-1037B & Bellcrank Rib Angels to the F-1029-R & L Bellcrank Ribs (respectivley), after which I clecoed the assemly to F-1078 (Forward Bottom Skin), the F-1006 (Bulkhead) and the F-1007 Frame.

Last but not lease, riveting the Bellcrank Ribs to the F-1007 Frame and to the F-1078 (Forward Bottom Skin).